assignmentssolution@gmail.com

Get Assignments and Projects prepared by experts at a very nominal fee.

More than 8 years in assisting assignments and projects/dissertation/thesis of MBA,BBA,BCA,MCA,PhD and others-

Contact us at : Email : assignmentssolution@gmail.com

Help for : SMU, IIBM,IMT, NMIMS, NIBM ,KSBM, KAIZAN, ISBM, SYMBIOSIS, NIMS, IGNOU, XAVIER, XIBMS, ISM, PSBM, NSBM, NIRM, ISBM, ISMRC, ICMIND, UPES and many others.

Help in : Assignments, projects, M.Phil,Ph.D disseration & thesis,case studies

Courses,MBA,BBA,PhD,MPhil,EMBA,MIB,DMS,MMS,BMS,GDS etc

Contact us at : Email : assignmentssolution@gmail.com



Tuesday 7 August 2012

Project management in IT_IIBM 2

IIBM Institute of Business Management
IIBM Institute of Business Management
Examination Paper MM.100
Project Management in IT
Section A: Objective Type (30 marks)
•This section consists of multiple choice questions and short notes type questions.
•Answer all the questions.
•Part One questions carry 1 mark each and Part two questions carry 5 marks each.
Part One:
Multiple choices:
1. The knowledge areas of Project Management Process Group are:
a. Planning and Initiating
b. Executing and Closing
c. Monitoring and Controlling
d. All of the above
2. To create a successful project, a project manager must consider:
a. Scope
b. Time
c. Cost
d. All of the above
3. Which one of the following is not involved in the top ten skills or competencies of an effective
project manager:
a. People skills
b. Leadership
c. Integrity
d. Technical skills
4. Another name of a phase exit is a _______ point.
a. Review
b. Stage
c. Meeting
d. Kill
5. Which process group includes activities from each of the nine knowledge areas?
a. Initiating
b. Planning
c. Executing
d. Closing
Examination Paper: Project Management
7
IIBM Institute of Business Management
6. The project team works together to create the ______.
a. Scope statement
b. WBS
c. WBS dictionary
d. Work package
7. __________ is a network diagramming technique used to predict total project duration.
a. PERT
b. A Gantt chart
c. Critical Path Method
d. Crashing
8. Which of the following is not a key output of project cost management:
a. A cost estimate
b. A cost management plan
c. A cost baseline
d. None of the above
9. CMMI Stands for:
a. Capability Maturity Model Integration
b. Complex Maturity Model Integration
c. Common Maturity Model Information
d. Capability Maturity Model Information
10. A proposal evaluation sheet is an example of:
a. RFP
b. NPV analysis
c. Earned value analysis
d. Weighted scoring model
Part Two:
1. Define Product Life Cycle.
2. What is Project Integration Model?
3. Write a note on Gantt charts.
4. What is Project Quality Management?
END OF SECTION A
Examination Paper: Project Management
8
IIBM Institute of Business Management
Section B: Caselets (40 marks)
•This section consists of Caselets.
•Answer all the questions.
•Each Caselet carries 20 marks.
•Detailed information should form the part of your answer (Word limit 150 to 200 words).
Caselet 1
A preliminary estimate of costs for the entire project is $140,000. This estimate is based on the
project manager working about 20 hours per week for six months and other internal staff working a
total of about 60 hours per week for six months. The customer representatives would not be paid for
their assistance. A staff project manager would earn $50 per hour. The hourly rate for the other
project team member would be $70 per hour, since some hours normally billed to clients may be
needed for this project. The initial cost estimate also includes $10,000 for purchasing software &
services from suppliers. After the project is completed, maintenance costs of $40,000 are included
for each year, primarily to update the information and coordinate the “Ask the Expert” feature and
online articles. Projected benefits are based on a reduction in hours consultants spend researching
project management information, appropriate tools and templates, and so on. Projected benefits are
also based on a small increase in profits due to new business generated by this project. If each of
more than 400 consultants saved just 40 hours each year (less than one hour per week) and could bill
that time to other projects that generate a conservative estimate of $10 per hour in profits, then the
projected benefit would be $160,000 per year. If the new intranet increased business by just 1
percent, using past profit information, increased profits due to new business would be at least
$40,000 each year. Total projected benefits, therefore, are about $200,000 per year.
Exhibit A summarizes the projected costs and benefits and shows the estimated net percent value
(NPV), return on investment (ROI), and year in which payback occurs. It also lists assumptions
made in performing this preliminary financial analysis. All of the financial estimates are very
encouraging. The estimate payback is within one year, as requested by the sponsor. The NPV is
$272,800, and the discounted ROI based on a three-year system life is excellent at 112 percent.
Discount rate 8%
Assume the
project is done
in about is
months
Year
0 1 2 3 Total
Costs 140,000 40,000 40,000 40,000
Discount
factor
1 0.93 0.86 0.79
Discounted
costs
140,000 37,037 34,294 31,753 243,084
Benefits 0 200,000 200,000 200,000
Discount
factor
1 0.93 0.86 0.79
Discounted
benefits
0 186,185 171,468 158,766 515,419
Discounted (140,000) 148,148 137,174 127,013
Examination Paper: Project Management
9
IIBM Institute of Business Management
benefits –
costs
Cumulative
benefits-costs
(140,000) 8,148 145,322 272,336 NVP
Payback in
year 1
Discounted
life cycle
ROI----
112%
Assumptions
Costs #hours
PM (500hours,
$50/hour)
25,000
Staff (1500
hours,
$70/hour)
105,000
Outsourced
software &
services
10,000
Total project
costs (all
applied in year
0)
140,000
Benefits
# consultants 400
Hours saved 40
$/hour profit 10
Benefits from
saving time
160,000
Benefits from
1% increase in
profits
40,000
Total annual
projected
benefits
200,000
Questions:
1. What according to you are the factors that can hamper the profit growth related with the
project?
2. Mention some strategies to further improve the project’s turnover.
Examination Paper: Project Management
10
IIBM Institute of Business Management
Caselet 2
Many organizations spend a great deal of time and money on training efforts for general project
management skills, but after the training, project managers may still not know how to tailor their
project management skills to the organization’s particular needs. Because of this problem, some
organizations develop their own internal information technology project management methodologies.
The PMBOKR Guide is a standard that describes best practices for what should be done to manage a
project. A methodology describes how things should be done, and different organizations often have
different ways of doing things. For example, after implementing a systems development life
cycle (SDLC) at Blue Cross Shield of Michigan, the Methods department became aware that
developers and project managers were often working on different information technology project in
different ways. Deliverables were often missing or looked different from project to project. They may
have all had a project charter, status report, technical documents (i.e., database design documents,
user interface requirements, and so on), but how they were producing and delivering these
deliverables was different. There was a general lack of consistency and a need for standards to guide
both new and experienced project managers. Top management decides to authorize funds to develop a
methodology for project managers that could also become the basis for information technology
project management training within the organization. It was also part of an overall effort to help raise
the company’s Software Capability Maturity Model level. BlueCross BlueShield of Michigan
launched a three-month project to develop its own project management methodology. Some of the
project team members had already received PMP certification, so they decided to base their
methodology on the PMBOKR Guide 2000, making adjustment as needed to best describe how their
organization managed information technology projects. See a complete article on this project on the
companion Web site for this text. Also see the Suggested Reading to review the State of Michigan
Project Management Methodology, which provides another good example of an information
technology project management methodology. Many organizations include project management in
their methodologies for managing Six Sigma projects. Other organizations include project
management in their software development methodologies, such as the Rational Unified Process
(RUP) framework. RUP is an interactive software development process that focuses on team
productivity and delivers software best practices to all team members. According to RUP expert Bill
Cottrell, “RUP embodies industry-standard management and technical methods and techniques to
provide a software engineering process particularly suited to creating and maintaining componentbased
software system solutions,” Cottrell explains that you can tailor RUP to include the PMBOK
process groups. Specifically, IBM Rational, the creators of RUP, found that it could adjust RUP input
artifacts with PMBOK process inputs, RUP steps with PMBOK process tools and techniques, and
RUP resulting artifacts with PMBOK process outputs.
Questions:
1. According to you what are the skills that needed for the project management of an organization?
2. How the six sigma project became a helpful tool in very sophisticated kind of project
management?
END OF SECTION B
Examination Paper: Project Management
11
IIBM Institute of Business Management
Section C: Applied Theory (30 marks)
•This section consists of Applied Theory Questions.
•Answer all the questions.
•Each question carries 15 marks.
•Detailed information should form the part of your answer (Word limit 200 to 250 words).
1. What is cost? What is the importance of Project cost Management and explain basic principles of
Cost Management.
2. Define the following:
a. Resource Histograms
b. Project Communication Management
END OF SECTION C